Turning Rooftops and Parking Spaces into Powerhouses
Granaita 260 kWp
The Sites
Phase 1 Complete: Castellana Green Powers Up
Castellana Green has hit an exciting milestone with Phase 1 now live—six solar PV systems delivering a combined capacity of 1,690 kWp. Key sites like Vallsur, El Faro, Granaita, and Puerta Europa are leading the charge toward a cleaner, more sustainable energy future.
With this momentum, Phase 2 is already in motion. Construction is set to begin in Q1 2025, expanding our mission to transform retail energy across Spain and Portugal.
| Phase 1: In operation | |||
|---|---|---|---|
| Site | Off-taker | Power | COD |
| Vallsur | Yelmo | 36 kWp | 13 July 2024 |
| Faro | Yelmo | 52 kWp | 19 July 2024 |
| Faro | Cactus | 532 kWp | 8 August 2024 |
| Granaita LC | Common Areas | 260 kWp | 26 August 2024 |
| Puerta Europa | Yelmo | 52 kWp | 25 September 2024 |
| Puerta Europa | Common Areas | 617 kWp | 23 October 2024 |
| Granaita GL | CityWok + Kaisen | 140 kWp | TBD |